Duna Terasz Grande, our main project has already exceeded the structural construction phase. Recently the masonry works are being completed by the general contractor, Kész Szerelő Zrt. The biggest single phase condominium project in the history of Hungary is constructed in good quality and on schedule, with expectzed handing over in Spring 2023. Our team

Renovation work has begun on the facade and entrance lobby areas of Atrinova Office Building in downtown Budapest. Újlaki Építő Kft. will carry out the modernisation of the facade of the office building on Bajcsy-Zsilinszky road based on the plans of Zsuffa and Kalmár Architect Studio. Our company performs the full technical supervision works on

The structural works of Duna Terasz Grande condominiums have reached 50% completion. Thanks to the rapid work of Fülöp Szerkezet Kft., the structural sub contractor and the general contractor Kész Építő Zrt, the construction of the reinforced concrete structure is progressing faster than the contractual schedule. This also means busy work for our technical supervision